Tejas Mk1A Delivery Status: From an August Target to a Reported March 2027 Date

The Tejas Mk1A, India’s upgraded light combat aircraft, missed the August–September 2026 window that Hindustan Aeronautics Limited (HAL) gave investors in May. Indian media now report a new commitment to deliver the first batch by 31 March 2027. We found no official HAL or Ministry of Defence statement confirming that date.
What HAL said on the record
On the company’s earnings call of 15 May 2026, HAL’s chairman said six F404 engines had arrived from GE, the aircraft fitted with them were flying, and some tests were still under way. Management hoped to resolve the remaining points and start deliveries by August or September.
The company also spoke of delivering around 20 aircraft in the 2026–27 financial year, linked to GE supplying roughly 15 to 20 more engines. HAL would not detail the technical refinements, saying design and development work goes through iterations.
Earlier, in February, HAL had said five Mk1A aircraft were fully ready for delivery and nine more had been built and flown, with GE engines awaited, News On AIR reported.
Where things stand now
According to Indian reports published in November, HAL committed after a review at Air Headquarters to hand over 16 to 18 jets by 31 March 2027, with hardware issues resolved and software work, including radar integration, in its final stage. The Week reported on 13 November that deliveries could begin in January 2027. These are press accounts, not contractual or official dates.
| When | Position | Status of the information |
|---|---|---|
| February 2026 | 5 aircraft ready, awaiting engines | HAL statement, via News On AIR |
| May 2026 | Start by August or September; about 20 in FY2026–27 | HAL management, investor call |
| November 2026 | Start possibly January 2027; 16–18 by 31 March 2027 | Media reports, not officially confirmed |
The orders behind the programme
The Air Force has two Mk1A contracts with HAL: 83 aircraft signed in early 2021, and a further 97 signed on 25 September 2025. The second, worth over ₹62,370 crore excluding taxes, covers 68 fighters and 29 twin-seaters, with indigenous content above 64%. Its deliveries are due to begin in 2027–28 and run for six years, the Ministry of Defence said.
Engines and radar
Engine supply from GE has been the most visible bottleneck, but it is not the only item that had to be closed: HAL itself referred to tests and refinements still pending in May.
On radar, the ministry’s 2025 release lists the indigenous Uttam AESA radar among the systems for the 97-aircraft order. HAL management said in May that Uttam was not coming into the 83-aircraft batch for now, pending production clearance from DRDO.
What this means
For the Indian Air Force, each slipped quarter delays the replacement of retired fighters. For HAL, the test is no longer building airframes but clearing them for acceptance and then holding a steady delivery rate while a second, larger order approaches. Until an aircraft is formally handed over, the order count, the number built and the number in service should not be confused.
Read more: from MiG-21 to Tejas, where India’s fighter replacement stands, and India’s latest large procurement clearances.
FAQ
Has the Indian Air Force received the Tejas Mk1A?
The November reports we reviewed still describe the first delivery as pending.
How many Tejas Mk1A aircraft are on order?
180 across the two contracts: 83 and 97.
Why is the Tejas Mk1A late?
Delayed F404 engines from GE are a major reason cited by HAL. In May the company also said some testing and refinement work remained.
Sources
- HAL earnings call transcript, 15 May 2026
- PIB: contract for 97 LCA Mk1A (25 September 2025)
- News On AIR: HAL clarification, 5 February 2026
- The Week, 13 November 2026
Last verified: 28 November 2026.

